Boram airport runway rehabilitation to begin in December at cost of K71.95 million

Rehabilitation of the Boram airport runway in East Sepik is due to start in mid-December 2026 and run until June 2028, at a cost of K71.95 million.

By PNG Sun · · 1 min read

Dugout canoes on the bank of the Sepik River
File photo: Dugout canoes on the bank of the Sepik River.

Work to rehabilitate the runway at Boram airport in East Sepik is expected to begin in mid-December 2026, the National Airports Corporation (NAC) said in a statement.

NAC said the project will cost K71.95 million and take 18 months, with construction running until June 2028. It is being carried out under the Civil Aviation Development Investment Project II (CADIP II), which is funded by the Government and the Asian Development Bank.

According to NAC, the work will add 290 metres to the south-east end of the runway, giving a total length of 2,010 metres. The project also covers pavement strengthening, asphalt surfacing, taxiways, the apron and parking bays, and a new terminal building.

The work will be done in 10 stages so the airport can stay open. In the first stage, the usable runway will be cut to 1,400 metres for a time.

NAC said the staged approach may bring temporary limits on operations during construction. It said airlines and aircraft operators would be told of operating requirements through Notices to Airmen, and urged operators to keep up to date with them.

The corporation said it would work with airlines, contractors and other aviation bodies to keep disruption to a minimum.